East Grand Avenue project begins
For the Rapids City Times
WISCONSIN RAPIDS – The Rapids East Grand Avenue Project begins April 8 with crews initiating street closures and detour routes. Erosion control and pavement removal are also planned to start this week.
The schedule is dependent on weather conditions and construction status. A full schedule may be found on the city’s website.
During construction, East Grand Avenue will be closed from Third Street to Eighth Street, with a detour utilizing Jackson Street.
The East Grand Avenue and Lincoln Street / East Jackson Street intersection will be closed during the second stage. This is scheduled to start mid-July and be completed mid-August.
The entire project is scheduled to be completed by November.
Updates will be made available on the city’s website https://www.wirapids.org/e-grand-ave-reconstruction.html.