Wisconsin Rapids City Times

Top Menu

  • Contact Us
  • E-Editions
  • Business Directory
  • Subscribe

Main Menu

  • News
    • Around the County
    • Government
  • Covid 19
  • Community
    • Community Calendar
  • Sports
    • Sports News
    • High School Sports Scores
    • Wisconsin Rapids Rafters
    • Wisconsin Rapids Riverkings
  • Arts & Entertainment
  • Obits
  • Opinion
  • Classifieds
    • View Ads
    • Place Ads
  • Legal Ads
    • Our Legals
    • Statewide
  • Contact Us
  • E-Editions
  • Business Directory
  • Subscribe

logo

Wisconsin Rapids City Times

  • News
    • Around the County
    • Government
  • Covid 19
  • Community
    • Community Calendar
  • Sports
    • Sports News
    • High School Sports Scores
    • Wisconsin Rapids Rafters
    • Wisconsin Rapids Riverkings
  • Arts & Entertainment
  • Obits
  • Opinion
  • Classifieds
    • View Ads
    • Place Ads
  • Legal Ads
    • Our Legals
    • Statewide
CommunityFeaturedGovernment
Home›Community›Centralia lot reconstruction to start Sept. 18

Centralia lot reconstruction to start Sept. 18

By Julie Schooley
September 17, 2019
3778
0
Share:

For the Rapids City Times

WISCONSIN RAPIDS – The reconstruction of the Centralia Parking lot is anticipated to start on Sept. 18.

City officials say that the reconstruction will occur in three phases, in an effort to keep the lot open as much as possible:

Phase 1 is expected to start on Sept. 18, with curb and gutter work on the islands and running electrical conduit for the replacement parking lot lighting. During phase 1 the parking lot will remain open and the majority of the asphalt will remain in place. The city’s contractor is anticipated to pour the curb and gutter the week of Sept. 23.

Phase 2 is scheduled to start Oct. 8, when city staff will begin work on the west half of the lot and the new entrance. Work will include removing asphalt, grading, as well as some curb and gutter work. Parking will be permitted on the remaining asphalt during phase 2.

Phase 3 is anticipated to begin Oct. 22. During this phase, city staff will be working on the east half of the lot. Work will include removing asphalt, grading, and some potential curb and gutter work. Patrons will be parking on the base material prepared in phase 2 during phase 3 repairs.

Finish grading and asphalt paving will take place on or about Oct. 28.

For more information, contact the Public Works Department at 715-421-8255.

Previous Article

Now That’s Entertainment

Next Article

Letter from the publisher: You do you ...

0
Shares
  • 0
  • +
  • 0
  • 0
  • 0
  • 0

Related articles More from author

  • Featured

    Krug, Schimel among Invited Guests at Tuesday’s ‘Pints and Politics’

    April 26, 2015
    By admin
  • Rafters logo
    FeaturedSports

    Rafters bring 9-4 Win Over Bombers

    August 2, 2015
    By admin
  • Rafters logo
    FeaturedSportsTop Stories

    Rafters Sweep Bombers, Improve to 28-33

    August 3, 2015
    By admin
  • EducationFeatured

    Stuff the Bus at Lunch by the River

    August 3, 2015
    By admin
  • FeaturedTop Stories

    Photo Gallery: Lunch by the River/Stuff the Bus

    August 7, 2015
    By admin
  • CommunityTop Stories

    ‘Evenings with Bernie’ to Feature Dem Debate Party

    October 11, 2015
    By admin
Copyright © 2020 Multi Media Channels LLC.
All Rights Reserved. No part of this publication or any of its contents may be reproduced, copied, modified or adapted without the prior written consent of Multi Media Channels LLC.
×